<menuitem id="pf55n"></menuitem>

<p id="pf55n"></p>
<noframes id="pf55n">
<pre id="pf55n"></pre>
<output id="pf55n"><output id="pf55n"><menuitem id="pf55n"></menuitem></output></output><pre id="pf55n"><output id="pf55n"><delect id="pf55n"></delect></output></pre>

<pre id="pf55n"><p id="pf55n"><delect id="pf55n"></delect></p></pre>

<pre id="pf55n"><p id="pf55n"></p></pre>

<output id="pf55n"></output><noframes id="pf55n"><p id="pf55n"><p id="pf55n"></p></p><noframes id="pf55n"><p id="pf55n"></p>
<p id="pf55n"></p>

<p id="pf55n"></p>

<p id="pf55n"></p>

<pre id="pf55n"><output id="pf55n"><delect id="pf55n"></delect></output></pre><noframes id="pf55n"><p id="pf55n"><output id="pf55n"></output></p>
<p id="pf55n"><output id="pf55n"></output></p>
<pre id="pf55n"></pre>

<pre id="pf55n"><p id="pf55n"><output id="pf55n"></output></p></pre>

<noframes id="pf55n"><p id="pf55n"></p>

<pre id="pf55n"></pre>

<pre id="pf55n"></pre><p id="pf55n"></p><p id="pf55n"><delect id="pf55n"><menuitem id="pf55n"></menuitem></delect></p>

土木公司泉州海灣大道項目百緯5路立交橋首聯現澆箱梁混凝土首次澆筑完成

發布日期:2020-04-27
【字體:打印

土木公司泉州海灣大道項目百緯5路立交橋首聯現澆箱梁混凝土首次澆筑完成

澆筑現場1.JPG


百緯五路首聯現澆梁施工航拍.jpg


4月24日上午,土木公司泉州海灣大道項目百緯5路立交橋首聯現澆箱梁混凝土首次澆筑完成。

據悉,百緯5路立交橋此次澆筑的首聯為左幅第5聯現澆箱梁,橋跨組成為3×30m,該橋總長為556m,共12聯,橋面寬16.8m,橋面高度最高達到9.8m,施工采用承插型盤扣式滿堂支架,施工難度大、工期緊、任務重。

為確保首聯現澆箱梁施工安全和質量,項目多次組織各方人員對技術復核、安全保障、原材供應、機具布置、人員準備等環節進行了周密安排和部署,嚴格執行技術規范,狠抓施工有利時機。在施工過程中,項目班子帶頭奮戰在施工一線,項目管理人員全程“零距離”把控施工進程,確保澆筑全程有序可控,實現了首聯現澆箱梁首次澆筑完成。

目前,項目百緯5路立交橋已完成樁基212根,完成進度已達到90%,墩身承臺已完成70%。此次首聯現澆梁箱梁混凝土首次澆筑完成,吹響了海灣大道項目上部結構施工的號角,為后續箱梁工作面提供了有利的基礎。(瞿陽、張昊)